Activity |
| Water Transmission & Distribution system |

- In 1991 MBE executed on Turnkey Basis 1400m3/hr Slurry Treatment & Water
distribution system of 3000 TPD Lead-Zinc Beneficiation Plant at the Rampura-Agucha mines
of Hindusthan Zinc Limited. Even now this project is regarded as a benchmark by experts in
the field.
- MBE commissioned the first Indian Washery way back in 1979. This project, again executed
on Turnkey basis, includes 1400m3/hr Waste Water Treatment Plant.
- MBE has also executed the Ash Water Recirculation system for Talcher Thermal Power
Station of National Thermal Power Station Ltd.
- For the Punjab State Electricity Board MBE has commissioned the extension of the
existing Ash Slurry, Plant Drainage, and Sludge Pipe-line.
- Slurry Pipe Line System at the Bailadila Mines of National Mineral Development
Corporation Limited has been completed.
- MBE has commissioned one of the largest combined Water Supply Scheme in the state of
Tamil Nadu covering 674 habitations in Trichy District for Tamil Nadu Water Supply &
Drainage Board, Chennai. The scheme has an 8 mm. dia. Collector Well, more 1000 km.
pipeline up to 700 mm. dia., 470 OHT, 31 Sumps & Pump Houses.
- Water Distribution project involving 12 km. MS Pipeline of 600mm to 1200 mm diameter and
45 km. 450 mm & 500 mm dia. DI pipeline for Ahmedabad Municipal Corporation
- Intake structure and 600 mm dia MS wrapped pipeline 3.6 km long for INDAL
at Hirakud
- Water Distribution System in Jodhpur for RUIDP has been completed. The project involved
commissioning 210 km AC & DI pipeline.
- Water distribution system in Ajmer city for RUIDP involving 98 km of AC & DI
pipeline.
|
|